Summer projects at area schools
Fri, 08/21/2015 - 11:45am
BRES
- Routine maintenance and cleaning
- Camera security completed first and second floors
- Grease trap rebuilt in kitchen
- Fuel tank/elevators/boilers/fire systems inspected
- Rear door boiler #1 repaired
- Planned replacement of two variable speed drives in the boiler room (September)
- Roof shingles replaced as needed
BRHS
- Routine maintenance and cleaning
- New carpet on the third floor hallway of the new addition area
- Fuel tank/elevators/boilers/fire systems inspected
- Planned replacement of the gymnasium bleachers (October)
Superintendent’s Office, Edgecomb Eddy School, Southport Central School, and Georgetown Central School: Routine maintenance and cleaning
Fire inspections all schools: Fire inspections for all sprinkler systems; exit signs; emergency lights; kitchen fire protection system; fire extinguishers; fire alarm panels; pull stations; smoke detectors; audio/visual strobes.